Lane Restriction-175' West of Meijer Ct & Meijer Dr intersection on Meijer Ct 2/4 to 2/28 storm pipe installation
Monday, February 4, 2019
Atlas Excavating will have a lane restriction approximately 175' West of Meijer Drive and Meijer Court intersection on Meijer Court for the installation of new storm pipe. Atlas will keep half the roadway open at all time to allow traffic to pass through the area. Contractor will utilize road construction signs, traffic barrels, barricades and flaggers. Construction crossing the road should be fairly quick and only take a few days. Then they will need time to allow for patching of the road. They are also allowing for poor weather. Contractor anticipates being done well before 2/28/19. Contact: Bret Dierdorf 812-243-2115